R.C. Thomas Hydroelectric Project
24 MW ETEC hydroelectric facility on the Trinity River near Livingston, TX
Estimated Commercial Operation: March 2020
Received FERC license in 3Q 2012
Turbine contract awarded in 2Q 2010
Executed EPC contract, approved August 2013
Commercial online date: July 2020
CREB – Received $10.2 million in 2008, $25 million in 2009, $15 million in 2011, and $56 million in 2015
Remainder to be funded by RUS.